Renovation of school building in Mbaash

Closed

In 2023, the foundation, together with a Dutch woman, made a donation of 425 Euro so that a school building in Mbaash could be renovated and fitted with a veranda. The donation request was as follows:

Primary school Mbaash, Tanzania

Project: Alteration of the building with classrooms 1 and 2 and the teachers’ room.

Reason: Preserving the building, no direct sunlight in the classrooms, safe shelter from the rain during lunch and breaks

Start: end of July 2023

End: beginning of August 2023

Duration: 2 weeks at most

Costs: 3,028,000 TZS -> €1244.25

Donation request €425

Project description:

The work will consist of extending the existing roof with extra roofing sheets, supported by a timber structure and iron posts.

In addition, a concrete floor will be laid under the extended roof along the whole length of the building.

The front of the building will be painted in the same colours as the other classrooms on the site.

Reason:

Preserving the building.

The building was one of the first in Mbaash and no longer meets today’s standard. The walls had also become less stable because the fierce sun, the strong sandy wind and the rain had free rein on the unpainted or half-painted walls (scorching of the walls).

The walls have since been repaired and a base coat of paint has been applied.

The veranda is needed for the future of the building and as the finishing touch.

Personally, I favour sustainable solutions, so: “keep what you have” rather than “just build new again”.

Timeline:

Because the workers are still on site, it saves money to carry straight on now. After all, once they have gone home we do not know when they will have time again, we would have to pay their travel costs and the season may work against us. Strike while the iron is hot.

Costs:

The head teacher drew up the budget together with the foreman. Materials are becoming ever more expensive in Tanzania, but even so it matches well with what I have done in recent times. I found no flaws in the budget and no “forgotten” costs such as transport of materials and/or the workers’ wages.

Supervision:

During construction I am in contact with the school almost daily and follow the progress of the work via FaceTime.

During the work…..

And before and after the work

Turned out beautifully, didn’t it?!